Zone A, shown yellow, denotes the ridge. This was inaccessible to survey but my Client confirmed that this area is insulated. However, it is unlikely that this area allows for cross ventilation. This zone will have new ventilated ridge tiles added to ensure that adequate ventilation is achieved.
Zone B, shown blue, denotes the areas of coved ceiling. These were currently filled with mineral wool insulation but to an insufficient depth to achieve the required U-value. The remedial works in this zone requires removing the existing insulation and replacing it with a modern PIR insulation brand, Celotex, which will not only achieve the required U-value with less depth of insulation but this will be installed with a 50mm air gap over, to ensure the ventilation requirements are achieved in this zone.
Zone C is currently a cold zone, with some insulation on the floor and partial polystyrene insulation (50mm depth) to the side walls adjacent the rooms. This is also inadequate. The remedial works in this zone will be to achieve a warm roof scenario, continuing the same level of insulation down from Zone B and repeating this all the way along between the rafters to eaves level.